We are now at the commissioning phase of this project, installing two back up 1250KVA and 400KVA generators are in place with 99% of the cabling installed.
Getting shutdowns and completing final terminations can be hard as you can understand as this is a working power station, the team get done a great job at AGL so far.
Both generators are now in position with cabling installed. We've completed arc fault and protection studies and will commence commissioning.